Expressing satisfaction over the progress of construction, the Chief Minister said that near about 55 percent work has been completed. Taking a pot-shot at Central government Babu claimed that Rs 1000 crore has not been released by the BJP government. The TDP Chief also slammed YCR Congress party for stalling the ongoing project.
The construction of biggest diaphragm wall took 414 working days for the final roll-out. Near about 2500 workers and 500 engineers were involved in the delicate task. The Chief Minister personally monitored the development with 25 physical inspections and 63 virtual inspections.
@wgodavarigoap @JaiTDP